Project File & Marketing Readiness

Run battery storage, PV, and grid connection projects as a project file. The evidence for maturity stages R0–R8 follows the German transmission system operators' maturity procedure and the checklists of banks and buyers. The tool shows the stage reached, the next steps, expiring deadlines, and when the project can be marketed.

Project data

Maturity stages and evidence

R0Site idea

0/3
  • 03Land parcels and area (ha) identified

  • 05Possible grid connection point with distance and voltage level named

  • 04Exclusion screening: protected areas and planning law (storage: privileged use § 35 (1) no. 11/12 BauGB; PV: development plan required?)

R1Land exclusive

0/2
  • 03Land register extract without conflicting encumbrances (sections II/III)

  • 03Written exclusivity from the owner, at least 7 months, not terminable for convenience

R2Grid requested

0/3
  • 05Grid connection inquiry or application filed (date, MW, voltage level)

  • 04Written permitting strategy

  • 06Outline technical concept: system description, site layout approx. 1:1000, schedule to commissioning

R3Grid secured

0/3
  • 05Binding, dated grid connection commitment or reservation (DSO) or accepted TSO offer with security paid

  • 05Conditions of a flexible connection agreement (ramps, balancing limits) documented – or none apply

  • 03Land rights: lease or easement agreement ≥ 10 years, or notarised option/reservation binding ≥ 12 months

R4Permit applied for

0/2
  • 04Building or BImSchG permit application filed (PV: resolution to draw up a development plan)

  • 04Reports available: noise, fire and water protection (AwSV), nature and species protection, soil

R5Permitted

0/3
  • 04Permit granted

  • 05Grid connection agreement signed or ready for signature

  • 03Easement granted, cable route and access secured

R6Ready to build

0/5
  • 04Permit final and non-appealable, no lawsuits and no conflicting third-party rights

  • 03All land rights secured in rem, term at least operation plus decommissioning

  • 05Construction cost contribution (BKZ) settled (amount and due dates)

  • 09Technical design and CAPEX estimate available

  • 04Construction not yet started

R7Final investment decision / construction

0/4
  • 09Financing committed, financial model with sensitivities (spread −20 %, degradation +20 %, CAPEX +10 %, grid delay 6–12 months)

  • 07EPC or battery supply agreement and O&M/LTSA signed

  • 07Revenue contract: tolling, PPA, optimiser or EEG award

  • 08Grid fee regime documented (date of investment decision, see note)

R8Commercial operation

0/2
  • 06Commissioning with acceptance reports

  • 08Registration in the Marktstammdatenregister

Valuation

Benchmark: RTB transactions in H2 2024 were at 45,000–62,500 €/MW (PF Nexus, indicative; more recent market prices are not publicly available).